| | | | | |  1) Spread portland cement according to the designed ratio. | 
2) Mix portland cement with in situ soil by grader. | 
3) Spray the mixture of polymer chemroad and water at the designed areas. | 
4) Mix portland cement with polymer chemroad and soil homogeneously. | 
5) Leveling and compacting with Pneumatic type rollers and steel-wheel rollers. | 
6) Light traffic can be opened after finished compaction 3-5 hours. | 
7) 3-7 days Curing with water after finished compaction. | 
8) Polymer chemroad soil cement with asphaltic pavement. |
| | | | | |
|